mdamores Lv3Posted 08 Nov 2023 10:14
  
this will be a very complex operation, and the steps will vary depending on the infrastructure and requirements. you may try the below:

1. back up your data before making any changes. backup should be separate from the existing data store to prevent data loss during the split
2. choose splitting method and create new datastore with the desired capacity and migrate data from the existing datastore to the new one.
3. you might be able to create new one within the existing datastore and move data in between if you are using LUNs
4. testing after the migration and monitoring
5. decommissioning of old datastore once you are confident that all data has been migrated successfully

I Can Help:

Change

Moderator on This Board

3
0
2

Started Topics

Followers

Follow

2
0
0

Started Topics

Followers

Follow

2
20
0

Started Topics

Followers

Follow

Board Leaders