1/4
Sangfor hDR: Choosing the Right Deployment Strategy for Large Data Environments

George Fady Lv2  Posted 2026-Oct-03 22:41

When designing a disaster recovery solution, deployment architecture and storage sizing can have a major impact on backup performance, recovery time, and overall DR efficiency.

Here are some useful points to consider when deploying Sangfor hDR:

1. Simplified hDR Deployment
The hDR system supports deployment on Sangfor HCI platforms. Importing the provided hDR VM template is the recommended approach, as it can simplify the installation process and reduce deployment time.

2. Consider the Network Bandwidth
For environments with large amounts of source data and relatively limited bandwidth between the source and destination sites, directly transferring all the data to the DR site may take an unacceptable amount of time.

In such scenarios, an alternative approach is to deploy the hDR platform on a physical machine at the source site.

This allows the initial data backup to be performed locally over a high-bandwidth connection, while the DR process can then be used to synchronize and fail over workloads to the destination environment when required.

3. Plan Storage Capacity Carefully
Storage sizing is another important consideration when designing an hDR environment.

As a general planning recommendation, the data disk capacity should be approximately 1.5–2× the amount of data that needs to be protected.

For example, if the disaster recovery data is 10 TB, planning approximately 15–20 TB of data disk capacity provides additional space for the DR workload and helps avoid insufficient storage capacity.

Key Takeaway:
A successful DR design is not only about having a recovery platform. You should also consider data volume, network bandwidth, deployment location, storage capacity, RPO/RTO requirements, and the expected recovery scenario.

Proper planning before deployment can significantly improve the efficiency and reliability of your disaster recovery strategy.

Feel alike? Bump to help this suggestion accepted by developers.

An accepted suggestion earns you 100 to 1000 coins. For more active members in Suggestions board, a badge Product Consultant may be rewarded. What is Coin?

Enter your mobile phone number and company name for better service. Go

Newbie585065 Lv3  Posted 2026-Oct-05 17:18
  
Thanks to share!
Humayun Ahmed Lv4  Posted 2026-Oct-05 14:08
  
Thanks to share!
Newbie006434 Lv2  Posted 2026-Oct-04 12:22
  
Very insightful post on hDR deployment for large environments! The simplified deployment via NDR VM template on HCI is helpful, and your advice about using physical server at source site for initial full backup over high bandwidth connection to save time is excellent. Also the storage planning tip of keeping 1.5x-2x of protected data capacity is very practical to avoid insufficient space. Thanks for sharing these design considerations!
Newbie900829 Lv2  Posted 2026-Oct-03 23:43
  
Excellent article! This is very important for large environments. You explained the key points perfectly - Simplified hDR deployment with OVA template, bandwidth consideration for large sites, and storage planning with 1.5x-2x capacity rule. The tip about using a physical server at source site for initial full sync to avoid WAN overload is really practical. Thanks for sharing these valuable deployment insights!
Newbie380273 Lv2  Posted 2026-Oct-03 23:02
  

Excellent guide George, thank you for sharing this!

Choosing right deployment strategy is very critical for large data environments. Many customers face long initial sync issue if they start replication directly over WAN.

I totally agree with your 3 points. From my experience, I want to add:

For large data like 10TB+, initial seeding locally on same LAN with hDR on physical machine is best, as you said. After first full sync, move incremental to DR site. This saves days of WAN transfer.

And storage sizing of 1.5-2x is very important. Many underestimate this and DR fail due to insufficient space when retention is enabled.

Proper planning of bandwidth, RPO/RTO and storage really makes DR project successful.

Thanks for this valuable insight!

#hDR #DRPlanning #Sangfor